Sunday, February 28, 2010

KITCHEN CABINETS STARTED

Cabinets throughout have started to go in.  Kitchen cabinets are the frameless variety veneered with an African Mahogany.  There were done locally.

From House 02 2010


From House 02 2010

From House 02 2010
From House 02 2010

Sunday, February 21, 2010

MAIN FLOOR CEILING

Finished up the main floor living room ceiling this weekend.  Edge trim and second coat of lacquer complete.  I am hoping the birch light/dark effect will coordinate with the variegated bamboo flooring to be installed next month.


From House 02 2010

From House 02 2010

From House 02 2010

From House 02 2010
From House 02 2010

Sunday, February 14, 2010

SIDING DETAILS

Siding started to go on this week.  Mixtutre of Hardie-Plank (Smooth 8" Lap) and Hardie-Panel (Smooth).  Plank installation is straightforward, but working some details on the panel installation.  Extruded aluminum trims (Z and H profile from Fry Reglet) will border all the panels which will be cut down to 4'x4' nominally.  Contractor wants to use washers with screws while we prefer just using a wafer head screw - pics show washers.


From House 02 2010

From House 02 2010

From House 02 2010

From House 02 2010

From House 02 2010
From House 02 2010

Saturday, February 6, 2010

WINDOW TRIM / INTERIOR DOORS

Windows are getting trimmed out and interior doors hung.  Main floor doors are solid core with VG Doug Fir veneer and lower level have birch veneer.

Clearstory Windows

From House 02 2010
VG Fir Door - Unfinished

From House 02 2010
Birch Door - Finished

From House 02 2010

From House 02 2010
From House 02 2010