Monday, December 28, 2009

DRYWALL STARTED

Drywalling has started in the basement. Bed and bath rooms are complete. Family area remains.

From House 12 2009

From House 12 2009

From House 12 2009

Sunday, December 27, 2009

WINDOWS

Windows were set the week before xmas. Entry door from Simpson is a VG doug fir 5 panel cross-reed glass with matching sidelight and transom. Windows and patio doors from Kolbe are extruded aluminum mill finish exterior with doug fir trim on the interior.

From House 12 2009

From House 12 2009

Living room interior / Patio exterior
From House 12 2009

From House 12 2009

From House 12 2009

Mud room interior / Patio exterior door
From House 12 2009

From House 12 2009

Saturday, December 19, 2009

PLANTER BOXES

The last week of warmer weather has allowed the front porch planter boxes to be poured and the forms stripped. The front steps will be contained between the boxes. Facing material for the boxes has yet to be determined.

From House 12 2009

From House 12 2009

From House 12 2009

From House 12 2009

Saturday, December 12, 2009

INSIDE PROGRESS

The house has been closed in for the last three weeks and the rough electrical, HVAC, and plumbing systems are complete. Foam insulation has been sprayed in walls and ceilings.


From House 12 2009


From House 12 2009


From House 12 2009